PROJECT OVERVIEW

When new student housing was required at an urban New Jersey college, precast concrete was the first and only choice. As a new cornerstone landmark for the campus, the design needed to be one that would both accommodate and represent the tech forward, innovative student body. With the next generation beginning their college selection process, students want single occupancy rooms and amenities that make student housing feel more like a home. This student housing offers bicycle storage, underground parking, a game room, creative space, lounge space, a grass courtyard, and indoor and outdoor cafes.

 

 

Precast Details

  • Owner: New Jersey Institute of Technology
  • Architect: Niles Bolton Associates, Inc.
  • Engineer of Record: O'Donnell & Naccarato
  • General Contractor: Terminal Construction
  • Project Size: 190,000 sq ft
  • Project Cost: $96 Million

Key Project Attributes

  • This student housing offers bicycle storage, underground parking, a game room, creative space, lounge space, a grass courtyard, and indoor and outdoor cafes.

 

  • The construction site was home to an existing 1908 public schoolhouse building. Part of the design of the new student housing was to incorporate the main entrance of the original schoolhouse into the student housing.

 

  • The one-level parking garage is home to a green roof, adding additional area for students to study in nature. 
Tell Us About Your Project

“To deliver a project of this size, scale, and magnitude, in the best of times, in less than two years is a heck of a feat,” said Andrew Christ, NJIT's Senior VP for Real Estate at the ribbon-cutting ceremony. “To do it during a global pandemic hovering over us was even more impressive. We persevered! We were nimble! We continued to stay the course!”

“This project is unique in that it was awarded, terms negotiated, state and city entitlements obtained, the facility designed and constructed during the COVID shutdown. Where numerous schools across the county put projects on hold, moving this project forward with so much uncertainty took a giant leap of faith.”-College Representative